The landed-cost guide for importers, 2026 edition: FOB to your dock, line by line
Landed cost line by line at the 2026 tariff stack: FOB, duty per HTS code (Section 301 lists, the July 24 layer, Section 232), freight per unit and the agent fee. One gasket moves at 11%; one enclosure stays in China.
This guide is for whoever has to sign off on an import program and defend the number afterward: the sourcing manager, the operations lead, the founder of a product brand that already buys overseas. It takes one part from the factory quote to your receiving dock, line by line, at the tariff stack in force as of September 26, 2026. Every rate below carries that date, and every rate is confirmed per HTS code before it goes on a quote.
The one-sentence answer: landed cost is FOB plus duty plus freight, and in 2026 the duty line moves more between origins than the factory price does, so a comparison that stops at FOB is wrong by roughly the margin that mattered.
Two parts run through the whole method. A molded gasket moves and nets 11% after the agent fee. A molded enclosure from the same buyer does not move at all. Both are the method working.
Why the factory price is the number that matters least
The factory price is the number everyone has. It sits on the pro-forma invoice, in the comparison spreadsheet and in the email thread, and because it is the easiest number to get, it becomes the number that gets compared. That habit was tolerable when duty was a few points of MFN at every origin. It is not tolerable now.
Look at the spread in the gasket example worked below. The FOB prices run $1.20, $1.26 and $1.38, a 15% range end to end. The duty lines run $0.48, $0.19 and $0.00. The factory price moved 18 cents across the origins; the duty moved 48 cents, and the origin with the highest factory price lands cheapest.
That is the general shape of 2026, not a quirk of rubber parts. A China-origin part on a Section 301 List 1–3 heading pays MFN plus 37.5 points as of September 26, 2026; the same part from an FTA-qualifying origin pays nothing, and from a 12.5% origin it pays MFN plus 12.5. No volume discount a factory can offer closes a 37.5-point gap on its own price.
The quote is a component, not an answer. What the FOB term covers, what it leaves out, and the mistakes buyers make lining supplier quotes up side by side are in FOB versus landed cost. For this guide, the rule is simple: rank nothing until all four lines are filled in for every origin.
The four lines: FOB, duty, freight, the fee
Line one is FOB. A quote marked FOB means the factory’s price includes getting the goods to the port of origin, export-cleared and loaded; everything from there is yours. In the US, customs value for an FOB purchase is essentially that FOB price, because international freight and insurance are not dutiable. Every percentage in the duty stack multiplies this number, which is why a higher FOB at a 0% origin can still land below a lower FOB at a 40% one.
Line two is duty, per HTS code. It is not one rate. It is the sum of the rates that apply to your 8-digit (sometimes 10-digit) HTS code at that origin: the Column 1 MFN rate, any China list rate, the July 24 Section 301 layer, and Section 232 where the part is metal. The next section reads that stack class by class.
Line three is freight to your dock. Ocean or truck, plus insurance, terminal handling and drayage, plus the two small federal fees collected at entry: the Merchandise Processing Fee at 0.3464% of value, capped, and the Harbor Maintenance Fee at 0.125% on ocean imports. Freight belongs on the sheet per unit, never per container, because a container of gaskets and a container of enclosures cost about the same to move and carry very different unit counts.
Line four is the agent fee. If a sourcing agent found and qualified the alternative, the fee is part of the alternative’s cost and belongs on its own line, not in a footnote. Ours is 10% of FOB, invoiced per PO, with no retainer, no setup fee and no minimum; you contract with and pay the factory directly, so there is no second margin hidden inside the FOB. The terms are on the pricing page, and the arithmetic on whether the fee earns its keep is in does a 10% sourcing fee pay for itself.
Lines one to three are landed cost. Lines one to four are all-in cost. The honest comparison is the incumbent’s landed cost against each alternative’s all-in cost, and that is how every table in this guide is built.
Reading the 2026 tariff stack by class
The stack changed four times this year, which is why the dates matter. On February 20, 2026 the Supreme Court struck the IEEPA reciprocal and fentanyl tariffs, and those amounts became refundable. From February 24 to July 24 a 10% Section 122 surcharge applied to most imports and expired on schedule. On June 8 the Section 232 metals regime was reset through December 31, 2027, and on July 24 USTR’s Section 301 action on 60 economies took effect: 12.5% on goods from China and most other economies, 10% on the rest, with FTA-qualifying goods and all Section 232 goods exempt.1
For China, the 12.5% stacks on the list rates in place since 2018 and 2019: 25% on Lists 1–3, 7.5% on List 4A, nothing on unlisted headings (List 4B was never imposed). For other origins it is MFN plus 12.5% (10% for some economies), unless the part is FTA-qualifying, in which case MFN is waived and no Section 301 applies. The rule of origin is checked per part, never assumed; a part that fails it pays MFN + 10%. All as of September 26, 2026.
That gives four classes of part, and the class decides more than the country does.
| Class of part | China | Alt. origin · 12.5% duty | Alt. origin · FTA, 0% |
|---|---|---|---|
| Section 301 Lists 1–3 | MFN + 37.5 points | MFN + 12.5 | 0% |
| List 4A | MFN + 20 points | MFN + 12.5 | 0% |
| Unlisted (List 4B, never imposed) | MFN + 12.5 | MFN + 12.5 | 0% |
| Section 232 metals (since June 8, 2026) | MFN + list rate + 232 at 50% or 25% | MFN + 232 at 50% or 25% | 232 at 50% or 25% (MFN waived) |
Lists 1–3 carry the gap that pays for a move: 25 points to a 12.5% origin, 37.5 points plus MFN to an FTA-qualifying one. List 4A carries only 7.5 points to a 12.5% origin, which a higher factory price erases quickly; against an FTA origin it is still MFN plus 20. Unlisted goods pay the same 12.5% from China and from a 12.5% origin, so only an FTA-qualifying origin changes the duty line.
Section 232 is its own class. It applies at 50% to articles essentially all steel, aluminum or copper and 25% to derivatives substantially made of them, on full customs value, at any origin. Under 15% metal content is exempt. Section 232 goods do not also pay the 12.5% or 10%, the China list rate still applies where the heading is listed, and an FTA waives MFN but not Section 232.
The step-by-step method for placing your own part in this table, from the entry summary to the final percentage, is in how to read your tariff stack by HTS code. Ten common parts already classified, from harnesses to cartons to fasteners, are in what the July 24 tariff change did to ten common parts. The metal case, where the duty gap between origins nearly vanishes and logistics decide, is in the June 8 Section 232 metals reset.
Before you ask which country, ask which class. A List 1–3 part is a candidate to move on duty alone; a List 4A or unlisted part needs the arithmetic done; a Section 232 part is a lead-time and MOQ question.
Freight per unit and transit working capital
Freight is the line buyers get wrong in both directions: overrated as a reason to stay close, underrated as a cost of staying far. The fix is the same for both errors. Divide the lane cost by the units that fit, and put the per-unit figure on the sheet next to duty.
Ocean transit from China and ocean transit from a 12.5% origin cost roughly the same per container, so for a dense part the freight line barely moves between them; the gasket pays $0.06 from one and $0.07 from the other. A short lane, truck freight in days instead of 30–45 on the water, is cheaper per unit for most goods and dramatically cheaper for bulky ones; the gasket’s FTA-qualifying origin pays $0.03. An illustration with round numbers: suppose a container costs $5,000 door to door. Holding 100,000 small gaskets, freight is 5 cents a unit; holding 5,000 bulky enclosures, it is $1.00 a unit.
Then there is the cost that never reaches the quote sheet. Goods on the water are inventory you have paid for and cannot sell. As an illustration, a $150,000 annual program with six weeks of transit at a 12% cost of capital carries roughly $2,000 a year in working capital on the ocean, which disappears with truck freight. Long, variable transit also means more safety stock at your warehouse, and ocean economics push toward full containers and quarterly releases where a supplier in truck range can ship monthly.
None of these decides a part alone. Together they are the tie-breaker when two origins land within a few cents. The lot-size and transit arithmetic, including how to cost a monthly release against a quarterly container, is worked in freight per unit, not per container. If the question you are really asking is whether truck range is worth a higher FOB, that is the nearshoring question, and it has the same answer as everything else here: run the lines.
Freight per unit, transit days and lot size all go on the sheet. The first is a cost line; the other two decide ties.
The two worked examples in full
The gasket moves. Molded EPDM gasket, HTS 4016.93.50 (MFN 2.5%, Section 301 List 3), 120,000 units a year, currently single-sourced in China at $1.20 FOB, freight to Dallas. Rates as of September 26, 2026, confirmed per HTS code.
| Per unit | China | Alt. origin · 12.5% duty | Alt. origin · FTA, 0% |
|---|---|---|---|
| FOB | $1.20 | $1.26 | $1.38 |
| Duty | $0.48 (40.0%) | $0.19 (15.0%) | $0.00 (0%) |
| Freight | $0.06 | $0.07 | $0.03 |
| Landed | $1.74 | $1.52 | $1.41 |
| Our fee, 10% of FOB | — | $0.13 | $0.14 |
| All-in | $1.74 | $1.65 | $1.55 |
| Annual, all-in | $208,800 | $197,520 | $185,760 |
Read it line by line. FOB rises as you leave China: 5% higher at the 12.5% origin, 15% higher at the FTA-qualifying one. Duty from China is MFN 2.5% plus List 3 at 25% plus the July 24 layer at 12.5%, 40.0% in total, or 48 cents on a $1.20 part. The 12.5% origin pays MFN plus 12.5%, 15.0%, or 19 cents; the FTA-qualifying origin pays nothing once the rule of origin is documented for the heading.
Landed, the incumbent is the most expensive of the three at $1.74. Adding the 10% fee to each alternative, the FTA origin lands all-in at $1.55 and the 12.5% origin at $1.65. On 120,000 units a year that is $23,040 a year, 11% after the fee, at the best origin, and $11,280 (5.4%) at the second. The factory price was 15% higher at the winner and it did not matter, because the duty line was 48 cents against zero and the freight line was half.
The enclosure stays put. Injection-molded PP enclosure, HTS 3926.90.99 (MFN 5.3%, List 4A), same buyer, same re-quote. The China stack is 5.3% plus 7.5% plus 12.5%, 25.3%; a 12.5% origin pays 17.8%; an FTA-qualifying origin pays 0%. It lands $2.77 from China, $2.79 from a 12.5% origin and $2.50 from an FTA-qualifying origin. Add 10% of FOB at the FTA origin and the net saving is under 1%.
Illustrative inputs that produce those figures: China $2.10 FOB, 25.3% duty, $0.14 freight; the FTA origin $2.45 FOB, no duty, $0.05 freight, $0.25 fee. Put that way, the move saves 53 cents of duty and 9 cents of freight against 35 cents more FOB and a 25-cent fee, which nets two cents. The recommendation is to stay in China and fix the inspection plan at the factory the buyer already has.
The reason is in the class, not the country. List 4A carries 7.5 points to a 12.5% origin instead of 25, the FTA origin’s 0% is worth 25.3 points instead of 40, and a similar FOB premium is applied to a $2.10 part instead of a $1.20 one. The same buyer, the same molding process and the same quote produced one 11% move and one stay. A method that cannot produce both answers is not a method.
What a re-quote should contain (and the as-of date discipline)
A re-quote is a document a CFO can read without calling you. That sets the standard for what has to be in it, and the list is short enough to check against any quote you receive, ours included.
- The 8-digit HTS code for the part, the full rate stack at each origin, and the date the rates were pulled.
- An FOB price per origin from a named factory, disclosed under NNN once the factory has been qualified for your part, with the MOQ and lot size behind that price.
- Freight per unit to your dock, with the lane, mode and transit days that produced it.
- The rule-of-origin status of any FTA-qualifying origin, proven for the heading, not assumed from the address.
- Tooling: who owns it, where it lives, and what it costs to duplicate or move.
- The agent fee on its own line, and the net saving after the fee against your current landed cost.
- A recommendation, including “stay put” when that is the answer, and the inspection plan that goes with whichever factory wins.
The as-of date is not decoration. A second Section 301 investigation, on excess capacity across 60 economies, opened in March 2026 and is still open, and the Section 232 reset runs through December 31, 2027. A quote with undated rates is a quote you cannot defend in a budget meeting six months later. Every figure in this guide is dated September 26, 2026, and every account gets a quarterly origin review so the sourcing decision stays current with the stack.
How the ten business days are spent, from the SKU list to the comparison, is laid out on the process page. If a quote is missing the HTS code, the date or the fee line, ask for it before you compare anything.
When China still wins
The enclosure is a common pattern, not an exception, and it is worth naming the others so that a move is a decision rather than a reflex.
China tends to win when the sub-supply chain lives there, as it does for electronics and complex assemblies where connectors, boards and hardware are all sourced within a day’s drive of the final factory. It tends to win when tooling needs to iterate quickly and the toolmaker and molder are in the same province. It tends to win on List 4A and unlisted headings, where the duty gap to a 12.5% origin is 7.5 points or zero and a higher FOB erases it.
It often holds on Section 232 metals, where duty is 50% or 25% from everywhere, an FTA waives MFN but not 232, and the remaining difference between origins is the 25% China list rate against freight and lead time. And on a small program, under roughly $50,000 a year, the cost of qualifying a second factory can exceed the duty saved regardless of class.
The decision rule is simple to state. Run China and the other viable origins at the real stack for the 8-digit code, with the fee on every alternative. If one origin lands 10% or more below the current cost, pursue it. If two land within 5% of each other, decide on lead time, MOQ and risk rather than price; if nothing beats the incumbent by 5%, keep the incumbent and fix the inspection plan, because a defect caught in the factory is cheaper than any duty saved at the dock.
Staying in China for a part does not mean staying single-sourced. Qualifying a second factory for the same part without moving the tooling is the China plus one program, and it is often the right answer for a List 4A part that should not move on duty but should not sit on one supplier either. The broader comparison of when each origin tends to win is in nearshoring versus offshoring in 2026.
“Stay put” is a valid output of the method. A re-quote that never produces it is selling you a move.
Running the comparison on your own parts
You can get most of the way to a decision before anyone quotes anything. Start with the parts that carry the most annual spend, because the method is the same per part and the savings scale with volume.
Pull the 8-digit HTS code for each from your broker’s entry summary; it is on every entry you have ever filed. Look up the Column 1 MFN rate in the HTSUS. Check which Section 301 list the heading is on, or whether it is unlisted, and whether the part is steel, aluminum or copper by more than 15% of its content. That places it in one of the four classes above and tells you the China stack and the alternative-origin stacks as of September 26, 2026.
Then run it through the landed-cost calculator with your actual FOB and MFN rate. Set the alternative-origin FOB multipliers to something conservative (5% and 15% above China is the gasket’s pattern) and enter freight per unit by lane. If the gap survives conservative inputs, it will usually survive a real quote. The five things the calculator cannot tell you, from rule-of-origin status to whether the factory can hold your spec, are in how to run a part through a landed-cost calculator.
Where the calculator says the gap is double digits on a List 1–3 part, get a real quote. Where it says the gap is under 5% on a List 4A part, you have saved yourself a qualification project and can spend the effort on the inspection plan instead.
The HTS code and the class do most of the sorting. The calculator confirms it; the re-quote prices it.
What to do with this
- List your top five parts by annual spend with their 8-digit HTS codes. Your broker’s entry summaries have the codes; your AP system has the spend.
- Classify each: Lists 1–3, List 4A, unlisted or Section 232. That single step sorts the candidates to move from the parts that should stay.
- Run the List 1–3 parts through the landed-cost calculator with conservative FOB multipliers and freight per unit. Note which clear 10%.
- Put a date on every rate you used, and a reminder to re-run the sheet each quarter. The second Section 301 investigation is open and the Section 232 reset expires at the end of 2027.
- For the parts that clear 10%, get factory-level quotes with the fee included and a rule-of-origin check per part. For the parts that do not, ask whether the current factory has ever been audited.
Want this run on your parts? Send up to five SKUs and you’ll have a landed-cost comparison — China and other countries, named factories — in ten business days. No fee, no obligation.
Footnotes
-
USTR’s stated basis for the 2026 Section 301 action was a finding on unenforced forced-labor import bans. It is a duty, collected at entry. It is not UFLPA, which is CBP’s import prohibition and detention regime, a traceability obligation rather than a tariff, and which applies regardless of what duty the goods pay. ↩